Framework agreement – A recap of relatively new information obligations introduced by the ECJ

 In the judgment C-23/20, the European Court of Justice ruled that the procuring entity has to publish certain information in the contract notice. Namely an estimated quantity and/or value, and a maximum quantity and/or value. In addition that the framework agreement will no longer have any effect once that maximum limit is reached.

This is, one could say, not an intuitive interpretation from the court. It comes to its conclusion in the light of i.e. the principles of equal treatment and transparency. The case probably requires procuring entities to change practices to adhere to it.